FREE E-Newsletter
Wings Magazine
Subscribe
  ABOUT US   |   CONTACT US   |   SUBSCRIPTION CENTRE   |   ADVERTISE   |   SITEMAP
MAGAZINE
Current Issue
Past Issues
News Archives
Web Exclusives
Video
Photo Gallery
 
MARKETPLACE
Aviation Books
Job Board
Classifieds
New Products
COMMUNITY
Events
AME Hall of Fame
100th Anniversary
Aviation Quiz
Association News
 
RESOURCES
A-List
E-Newsletter
Links
Sitemap
Careers in Aviation
Publications
Helicopters Magazine Careers in Aviation
Production Resumes on Boeing 787 Dreamliners with Fifth Flight-Test Airplane
787Jan. 30, 2009, Everett, WA - Production of Boeing resumed yesterday with the join of the fifth airplane designated for flight test. This airplane, designated ZA005, is the first to be powered with General Electric GEnx engines. The major assemblies were loaded in final body join over the past several days. The fuselage and wing joins occur simultaneously.

"This airplane signifies our return to a steady production rhythm," said Jack Jones, vice president of 787 Final Assembly and Change Incorporation.

"Sections are arriving in Everett at the completion levels committed by our partners and close to what is expected for mature production," Jones said. "The substantial progress made by our partners streamlines the assembly process, which is essential as we ramp up production."

Five of the six airplanes designated for flight test are now in varying stages of production. Power was restored earlier this week to the first flight-test airplane, ZA001, and production testing has resumed as the airplane prepares for first flight in the second quarter. Rolls-Royce engines are hung on ZA002, in the fourth and final production position in the factory. The third and fourth flight-test airplanes, ZA003 and ZA004, are in the third and second production positions, respectively.

Fastener rework is done on ZA001, nearly complete on ZA002 and progressing well on the third and fourth airplanes, Jones said. "We have applied the resources necessary to complete all the outstanding work on these airplanes and keep the production line moving forward."

Assemblies for the final flight-test airplane, ZA006, are in production at partner sites worldwide. In all, assemblies for 30 Dreamliners are in production at this time.

The 787 Dreamliner has orders for 895 airplanes from 58 airlines.

 
   